At what point do projects funded under the competitive resilience program need to be listed in the TIP and STIP?

Pre-construction activities (i.e. planning, NEPA review, preliminary engineering and design) are not required to be on the TIP and STIP prior to incurring costs to be eligible for potential reimbursement under pre-award authority. FTA considers these activities necessary to estimate the cost of a project for inclusion in the TIP and STIP.

All other project activities must be in the TIP and STIP prior to incurring costs.

FTA will determine the eligibility for reimbursement of pre-award activities once a grant is in development and the project has been included in the TIP and STIP.