BPPM Liquidated Damages Checklist
Sample form:
LIQUIDATED DAMAGES CHECK LIST
BART PROJECT NO. ___________ CONTRACT TITLE: ___________
ESTIMATED CONTRACT VALUE:
General ____________ Mechanical ____________Electrical ______________ Other ______________
Item
Project Manager's Determination
If Applicable, Dollar Amount
Applicable
Non-Applicable
1. Costs reflecting the relative importance of completion of this contract to the completion of other directly associated activities, e.g., if a $10 million dollar substation is being procured and requires construction of a building, the cost to BART of delays upon the completion of the building on the substation procurement should be considered.
2. Rental costs for each day of facilities and equipment necessitated by the delays in contract completion.
3. Cost(s) for additional maintenance required on equipment or structures being replaced for each day of delay in completion of the project.
4. Additional operating costs to BART for each day of delay in completion, including but not limited to cashier, operator and supervisory costs resulting from contract completion delays. Costs of route detours or substitution of one transit mode for another shall be considered.
5. Loss of revenue to BART's operations for each day due to delay in contract completion.
6. Any other damages for each day of delay in completion which BART may anticipate, e.g., is there a high potential for delay of one prime contract with resulting costs to BART for the other prime contracts.
7. Estimated costs of inspection.
8. Actual damages (Project Manager to indicate whether actual types of damages should be excluded from the calculations).
SIGNED _________________________
PROJECT MANAGER